EPC contract - Project "Operational Continuity Assurance of Thickeners Tailings for Concentrator Plant ". Codelco Chuquicamata.

 

Client: Codelco
Industry: Mining

The projects consist of design, supply and build the required modifications for 2 thickener tailings of a concentrator plant, to increase significantly resilience of water and effectiveness in the process. It requires the deployment of engineering field to face dynamically the characteristics of existing installation interference, the design of new equipment in pump rooms, the design of the entire system of 2 large -diameter thickeners, design and construction of civil and hydraulic works and replacement of control and electrical installations.